ISO / RTO Market Series

Battery Opportunities in PJM

What exists now, what is coming, and how a developer-owner makes money in the country's hottest capacity market.
Goal of this analysis

Determine what battery storage opportunities exist in PJM today and over the next several years, and identify the levers that move a project from marginal to investable.

Analysis dated 15 July 2026  ·  Charts and figures added 3 August 2026 (no analytical changes)  ·  Developer / investor lens  ·  Every figure carries a cited source. VERIFIED = primary source; ESTIMATE = modeled or triangulated.
Hand-drafted perspective drawing of the eastern United States with the PJM territory raised above the map as a translucent teal panel, transmission nodes rising from it, and a white clay model of a utility-scale battery installation in the lower right corner
Diagrammatic illustration, not a service-territory map. The raised panel indicates the PJM footprint conceptually; boundaries, nodes, and transmission lines are illustrative and are not survey-accurate. PJM's actual territory covers all or part of 13 states plus the District of Columbia: Delaware, Illinois, Indiana, Kentucky, Maryland, Michigan, New Jersey, North Carolina, Ohio, Pennsylvania, Tennessee, Virginia and West Virginia. ILLUSTRATION Produced for this report; verify any footprint question against PJM's own territory map at pjm.com.
Read first

The seven things that matter

1
Capacity prices have repriced roughly 11x in three years, $28.92 → $329.17 → $333.44 per MW-day, and the last two auctions both cleared at the FERC-approved cap. This is the single biggest tailwind for a PJM battery.
2
Yet PJM has almost no batteries operating (~0.4–0.7 GW) versus ~25 GW across ERCOT and CAISO. The runway is enormous and largely empty.
3
Data centers are driving more than 100% of near-term load growth. Without them PJM's peak would be flat-to-shrinking; the most recent auction cleared ~6.6 GW short of the reliability requirement.
4
Four revenue streams stack: capacity, energy arbitrage, frequency regulation, and reserves. A well-sited 4-hour battery is benchmarking ~$288–304/kW-yr on recent run-rates, though that reflects an exceptional 2025 price environment.
5
Timing is gated by interconnection. A plain-vanilla new project is a ~2030–2032 story. The shortcuts: buy an already-studied queue position, or co-locate behind existing rights using Surplus Interconnection Service.
6
Merchant economics are real but thin on their own; the state incentive is what makes them investable. A New Jersey GSESP award flips the flagship 100 MW / 4-hr case from −$28.7M to +$35.5M NPV (5.4% to 11.1% IRR). The 30% federal ITC is not available for this strategy (see note below).
7
Best states right now: New Jersey (live incentive auctions), Maryland (1,600 MW mandate), Virginia (expanded VCEA + data-center epicenter). Even no-mandate states (PA, OH) work on capacity-market strength alone.
The setup

Why PJM, why now

Three forces have converged: a capacity market that has repriced by an order of magnitude, demand growth that is structurally driven by data centers, and a storage fleet that has barely started to build.

$329/MW-day
2026/27 capacity clearing price (at the cap), +22% YoY
PJM 2026/27 BRA Report VERIFIED
$16.1B
Total 2026/27 capacity auction cost (+9.5%)
PJM 2026/27 BRA Report VERIFIED
~0.4–0.7GW
Operating battery capacity in PJM today
Modo Energy / Cleanview ESTIMATE
66.5GW
Standalone storage in PJM's new Cycle 1 queue
PJM Inside Lines, Apr 2026 VERIFIED
PJM capacity clearing price, RTO ($/MW-day) $342023/24 $292024/25 $2702025/26 $3292026/27 $3332027/28 Both at the cap
Source: PJM Base Residual Auction Reports for 2025/26, 2026/27, 2027/28 (pjm.com), accessed 15 Jul 2026. VERIFIED
The runway
PJM storage: what exists, what is needed, what is queued (GW) Operating today 0.4–0.7 GW Forecast operating 2030 ~7 GW Needed by 2032 16 GW Needed by 2045 43 GW Standalone in Cycle 1 queue 66.5 GW 020 4060
Operating Forecast operating Resource-adequacy requirement Interconnection queue (not built)
These bars are four different quantities on one axis, not one time series. Operating capacity is what exists; the requirement bars are what PJM is assessed to need; the queue bar is applications, and historically only a fraction of any queue is built. The gap between the first bar and the third is the opportunity this report is about.
Sources: operating fleet, Modo Energy / Cleanview ESTIMATE; 2030 forecast, Modo Energy ESTIMATE; 2032 and 2045 requirements, Brattle via Utility Dive VERIFIED; queue, PJM Inside Lines Cycle 1 window closed 27 Apr 2026 VERIFIED. All accessed 15 Jul 2026.
The demand engine. PJM's 2026 Long-Term Load Forecast has summer peak rising from ~160 GW (2025) to ~253 GW by 2046, with the near-term 10-year growth rate raised to 3.6%/yr. Between 2026 and 2031, data centers account for ~35.1 GW of ~34.6 GW of total growth, over 100%. Reserve margins are tightening: the 2027/28 auction cleared ~6.6 GW short of the reliability requirement.
Sources: Modo Energy, "Data centers define PJM's 2046 load forecast"; Utility Dive; PJM Inside Lines (accessed 15 Jul 2026). VERIFIED
How a battery earns

The four revenue streams

PJM co-optimizes energy, regulation, and reserves in a single dispatch; capacity is a separate forward obligation. A battery stacks all four. Figures below are for a 4-hour system, per kW-year.

StreamWhat it isConservativeStrong / recentBasis & source
Capacity (RPM)Forward payment for being available at peak; accredited via ELCC$49–60$60+PJM BRA price × 50% ELCC × 365 VERIFIED
Energy arbitrageBuy low / sell high on the day-ahead & real-time spread (TB4)$40–60$69+ grossModo TB4: $47 (2024) → $69 (2025), ~$112 by 2030 ESTIMATE
Frequency regulationRegD fast signal, batteries' historical stronghold$60–120$200–2602024 RMCP $31.86/MW; Modo Q1-25 peak ESTIMATE
ReservesSynchronized / primary / 30-minute, opportunistic adder$3–15$15–252024 SRMCP $3.20/MWh ESTIMATE
All-inStacked, co-optimized~$150–255~$288–304Modo PJM benchmark run-rate ESTIMATE
Where the money actually comes from
Revenue range by stream, 4-hour system ($/kW-yr) Left dot = conservative underwriting · Right dot = strong / recent run-rate Frequency regulation $60–260 Energy arbitrage $40–69 Capacity (RPM) $49–60+ Reserves $3–25 All-in, stacked $150 $304 $0$80 $160$240$320
Read the widths, not just the positions. Regulation is by far the widest bar, which is the same as saying it is the least reliable line in the model: it is both the biggest earner and the one that has already collapsed once. The all-in range is deliberately narrower than the sum of the four highs, because the streams do not peak in the same year.
Sources as per the table above: PJM BRA price × 50% ELCC × 365; Modo Energy TB4 spread and PJM benchmark; Monitoring Analytics 2024 State of the Market, Sec. 10. Component ranges and all-in benchmark are ESTIMATE except the capacity calculation basis VERIFIED. Accessed 15 Jul 2026.

Capacity is the anchor, and the story

Storage is accredited on a marginal ELCC basis. For the 2026/27 auction, PJM rates a 4-hour battery at 50% of nameplate, a 6-hour at 58%, 8-hour at 62%, and 10-hour at 72%. Because accreditation is marginal, short-duration ratings decline as storage saturates, which is why the market is pushing developers toward longer duration.

ELCC accreditation by duration, 2026/27 50%4-hr 58%6-hr 62%8-hr 72%10-hr 0% 75%

Source: PJM ELCC Class Ratings for the 2026/2027 BRA (pjm.com), accessed 15 Jul 2026. VERIFIED, note several trade-press figures circulating are wrong; these are the official ratings. Ratings shown are for the 2026/27 auction only and decline as storage saturates, because accreditation is marginal.

Regulation: real money, real saturation risk

RegD is where batteries have always earned the most, and 2024–25 prices rose sharply (2024 clearing +40% YoY). But the requirement is small (~525–800 MW) and the market saturated once before, RegD prices fell roughly two-thirds after the 2014 build-out. The 2024–25 rise is a cyclical rebound, not a structural repeal. Do not underwrite to today's peak.

Source: Monitoring Analytics 2024 State of the Market, Sec. 10; Utility Dive. VERIFIED

Getting connected

Interconnection and timing, the real gate

Revenue is attractive; the binding constraint is getting steel in the ground. PJM has overhauled its queue, and a set of shortcuts is emerging.

Three doors onto the grid
Time to commercial operation, project started today 2026 2027 2028 2029 2030 2031 2032 Co-location / SIS COD ~2–3 yrs Buy a studied position COD 2027–2029 New build, full queue COD 2030–2032
Development and interconnection Commercial operation window
The revenue case is roughly the same down all three routes. The difference is years, and years are what decide whether a project catches today's capacity prices or someone else's. This is why route selection, not siting, is the first decision.
Sources: PJM Inside Lines; Modo Energy; K&L Gates and Blank Rome analyses of FERC Docket EL25-49 (order issued 18 Dec 2025), accessed 15 Jul 2026. Timelines are ESTIMATE; the co-location route remains pending PJM's final compliance tariff.
Aerial wireframe illustration of a data center with an adjacent battery storage yard and substation sharing one transmission interconnection
The structure the FERC order unlocks: storage (teal) sited beside data-center load, sharing the existing interconnection rights at the substation (orange) rather than taking a new queue position. Illustration produced for this report; diagrammatic, not a specific site.
Realistic time-to-COD for a project started today: a plain-vanilla new build is ~2030–2032 (4–6 years). Buying an already-studied Fast Lane / TC1 position targets 2027–2029. A co-location / SIS structure behind existing rights, with no upgrades, can compress to ~2–3 years, pending PJM's final compliance tariff.
Sources: PJM Inside Lines; Modo Energy; K&L Gates and Blank Rome analyses of FERC Docket EL25-49 (accessed 15 Jul 2026). VERIFIED
Where to build

State-by-state opportunity

PJM-wide capacity prices lift merchant economics everywhere, but state programs decide where the incentive money and mandates are. Ranked for a developer.

StateStatusInstrumentThe numberWhat it means for a developer
New Jersey LIVEAwarding nowGarden State Energy Storage Program (GSESP)Tranche 1 = 355 MW awarded Mar 2026; Tranche 2 (645 MW) open, bids due 7 Aug 2026Fixed 15-yr incentive, lowest $/MW-of-accredited-capacity wins. De-risks merchant revenue. VERIFIED
Maryland LIVEProcuringNext Generation Energy Act (NGEA, 2025)Up to 1,600 MW transmission (two 800 MW rounds) + 150 MW distribution; Round 1 oversubscribed (1,375 MW applied)≥4-hour duration required; 24-month build deadline. Large mandate, early stage. VERIFIED
Virginia LIVEMandate + loadVCEA as amended (HB2537, 2025)Dominion 5,220 MW by 2045; 35% third-party ownership floorData-center epicenter (demand may double in 10 yrs). Third-party floor is the merchant entry point. VERIFIED
Illinois (ComEd) NEWEnacted Jan 2026Clean & Reliable Grid Affordability Act (CRGA)3,000 MW by 2030; first procurement 1,038 MW (588 MW in PJM/ComEd)20-yr Indexed Storage Credit. Only the ComEd zone is PJM. VERIFIED
Pennsylvania NO MANDATECapacity-drivenNone enacted (Shapiro "Lightning Plan" proposed)PJM capacity at the cap ($329/MW-day)Pure merchant + capacity play; storage is not AEPS-qualifying. VERIFIED
Ohio NO MANDATETax + loadHB 15 (2025)Storage TPP tax cut to 7% from TY2027; AEP Ohio queue 30+ GWTax-advantaged, data-center-heavy. Merchant + capacity. VERIFIED
Program size, and how much of it is reachable
State storage targets (MW) and what is procurable now Virginia 5,220 by 2045 35% third-party floor ≈ 1,827 MW is the merchant entry point Illinois (ComEd) 3,000 by 2030 only 588 MW of the first procurement sits in PJM/ComEd Maryland 1,750 total Round 1 (800 MW) already oversubscribed at 1,375 MW applied New Jersey 1,000 GSESP Tranche 2, 645 MW, bids due 7 Aug 2026 — the only door open right now Pennsylvania · Ohio No mandate. Merchant plus capacity revenue only.
Total program / mandate Near-term procurable or reachable slice
Bar length is not opportunity. Virginia is the largest number and the slowest clock (2045); New Jersey is the smallest and the only one with a bid date inside this quarter. Target the dark segments, not the long bars.
Sources: NJ BPU orders (Docket QO22080540) & Utility Dive; MD PSC / Next Generation Energy Act 2025; VA enrolled HB2537 & JLARC Report 598; IL Public Act 104-0458 / Illinois Power Agency; PA PUC AEPS; OH HB15. All accessed 15 Jul 2026. VERIFIED program volumes; the Virginia 1,827 MW figure is the stated 35% floor applied to 5,220 MW ESTIMATE (arithmetic, not a procurement commitment).

Sources: NJ BPU orders & Utility Dive; MD PSC / NGEA; VA enrolled HB2537 & JLARC Report 598; IL Public Act 104-0458 / IPA; PA PUC; OH HB15 (Kroll, Dickinson Wright). All accessed 15 Jul 2026.

Federal overlay

Why this analysis does not use the ITC

Important: no ITC in this analysis

Every number in this report and the accompanying pro forma excludes the 30% federal Investment Tax Credit. Not as a modeling preference, but because there is no credible FEOC-compliant battery manufacturer at competitive pricing as of mid-2026. The domestic products marketed as "FEOC-compliant" are 2027 promises that price above a Chinese LFP battery even with the full US tariff stack added, and disclose no cell or cathode origin. The affordable, available battery in this strategy is Chinese-content, which fails FEOC, so the credit is simply off the table.

The credit exists in law

Under the 2025 OBBBA, standalone storage was carved out of the wind and solar cliff and stays on the §48E schedule: base 6%, up to 30% with prevailing-wage and apprenticeship. So on paper the credit is available to storage.

Source: IRS Clean Electricity Investment Credit; Kirkland & Ellis OBBBA analysis. VERIFIED

But FEOC is a hard gate, and the hardware to clear it is not competitive

Eligibility requires ≥55% non-prohibited-foreign (non-China) content in 2026, pass/fail. Checking the manufacturers directly (eticaag.com, agbess.com), the "FEOC-compliant" products are future (2027) with no cell-origin proof, and cost more than a tariffed Chinese battery. So the credit is unreachable at a net gain today.

Sources: IRS Notice 2026-15; manufacturer sites eticaag.com, agbess.com (accessed 15 Jul 2026). VERIFIED

Also on the radar: the Section 301 tariff on Chinese grid batteries rose from 7.5% to 25% effective 1 Jan 2026 (roughly +15–20% on delivered cell cost), and even so the Chinese battery undercuts the domestic FEOC-compliant options. FERC Order 841 (storage in wholesale markets) is fully live in PJM; Order 2222 (DER aggregation) has slipped to a proposed Feb 2028 go-live.
Sources: Morgan Lewis; FERC; Renewable Energy World. VERIFIED
The economics

What the numbers say

We modeled four configurations, 20 MW and 100 MW, each at 4-hour and 2-hour duration, as unlevered, pre-tax, merchant projects on gross CAPEX with no ITC, at an 8% discount rate and a ~2030 COD. Full live-formula model in the accompanying workbook.

ConfigurationInstalled CAPEXYr-1 revenue
($/kW-yr)
NPV @ 8%IRRSimple payback
20 MW / 4-hr$34.5M$226−$7.6M4.7%11.2 yr
100 MW / 4-hr (flagship)$164.5M$226−$28.7M5.4%10.6 yr
20 MW / 2-hr$23.0M$192−$0.05M8.0%8.4 yr
100 MW / 2-hr$109.8M$192+$5.7M8.8%8.0 yr

Source: PJM_BESS_ProForma_v2.xlsx, live-formula model, results verified via recalculation 15 Jul 2026. No ITC. Revenue assumptions triangulated from PJM, Monitoring Analytics, and Modo Energy; cost assumptions from NREL/TP-6A40-93281 and Lazard LCOS v10. ESTIMATE (model output).

The single most important chart in this report
NPV @ 8%, merchant base vs. with NJ GSESP ($ millions) Unlevered, pre-tax, gross CAPEX, no ITC, ~2030 COD $0 −$25M +$25M +$50M 20 MW / 4-hr −$7.6M +$5.3M 100 MW / 4-hr flagship −$28.7M +$35.5M 20 MW / 2-hr −$0.05M +$12.8M 100 MW / 2-hr +$5.7M +$69.9M
Merchant base, negative NPV Merchant base, positive NPV With NJ GSESP incentive
Three of the four configurations do not clear an 8% hurdle on merchant revenue alone. All four clear it comfortably with the New Jersey incentive. With the federal ITC unavailable, this chart is the argument for leading with a state program rather than a merchant site: the incentive is not an enhancement to the deal, it is the deal.
Source: PJM_BESS_ProForma_v2.xlsx, live-formula model, results verified via recalculation 15 Jul 2026. ESTIMATE (model output). GSESP modeled at $75k/MW-nameplate-yr for 15 years, within the $60k–82k/MW-yr range of actual NJ awards; additive mechanic verified from NJ BPU Order 18 Jun 2025, Docket QO22080540.

Two findings worth pausing on

  • On a pure merchant basis, 2-hr out-returns 4-hr. Regulation is power-based, so it pays the same for both durations, while 4-hr costs roughly twice the energy CAPEX. The 4-hour's real edge is capacity accreditation (50% vs ~35% ELCC), a hedge against future long-duration value, and eligibility for programs that require ≥4-hour (Maryland).
  • Scale helps. The 100 MW cases spread fixed development and O&M over more MW, lifting IRR versus the 20 MW twins.

The New Jersey incentive is what makes it investable

With the ITC unavailable, the state program is the lever. New Jersey's GSESP fixed payment stacks additively on PJM revenue for 15 years (verified from the order: no offset, no clawback). It flips every case strongly positive:

ConfigurationBase NPV / IRR+ NJ GSESP NPV / IRR
20 MW / 4-hr−$7.6M / 4.7%+$5.3M / 10.2%
100 MW / 4-hr−$28.7M / 5.4%+$35.5M / 11.1%
20 MW / 2-hr−$0.05M / 8.0%+$12.8M / 15.8%
100 MW / 2-hr+$5.7M / 8.8%+$69.9M / 16.9%

NJ awards ran $60k–82k/MW-nameplate-yr; model uses $75k. Additive mechanic verified from the order text. Source: NJ BPU Order 18 Jun 2025, Docket QO22080540; pro forma Scenarios tab. VERIFIED mechanic, ESTIMATE rate.

Bottom line on economics. Merchant-only PJM storage is a thin-margin proposition at an 8% hurdle, an honest floor, not a forecast. With the ITC off the table, the New Jersey incentive is the decisive lever: it flips the flagship case from −$28.7M to +$35.5M NPV and lifts IRR from 5.4% to 11.1%. Capacity revenue and co-location (which cuts cost and years) do the rest. The strategy lives or dies on the state program, not the tax credit.
Recommendation

How to play PJM

Aerial site plan of a data center and an adjacent fenced battery storage compound connected through a shared switchyard to a transmission corridor
What "chase co-location" looks like on the ground: the battery compound and the data center meet at a shared switchyard on one set of interconnection rights, with the transmission corridor already in place. No new queue position, no network upgrades, which is the condition the FERC order attaches to the fast path. Illustration produced for this report; diagrammatic, not a specific site, and container count does not imply a rating.
The next five years

Outlook to 2030

~7GW
PJM operating storage by 2030 (Modo), a ~17x jump
Modo Energy ESTIMATE
16GW
Storage PJM needs by 2032 (Brattle resource adequacy)
Brattle via Utility Dive VERIFIED
43GW
Storage PJM needs by 2045 (Brattle)
Brattle via Utility Dive VERIFIED
~$112k/MW-yr
Forecast 4-hr arbitrage spread by 2030 (highest of Eastern ISOs)
Modo Energy ESTIMATE

The direction is unambiguous: PJM is structurally short of capacity, demand is climbing on data centers, and storage is the fastest resource to build. The open questions are price durability (does the capacity cap hold or lift after 2027/28; how fast does regulation saturate) and execution (interconnection throughput and FEOC-compliant supply). For a developer who can move now, via a live state program, an already-studied position, or a co-location structure, the window is wide and largely uncontested.

Provenance

Sources

Capacity market: PJM 2026/27 & 2027/28 Base Residual Auction Reports (pjm.com); PJM ELCC Class Ratings 2026/27; Brattle/PJM CONE 2026/27 Report; RTO Insider & Utility Dive (Shapiro cap/floor settlement, FERC ER25-1357).

Energy & ancillary: Monitoring Analytics 2024 State of the Market Report for PJM (Sec. 10); Modo Energy PJM benchmark, TB4 spread and outlook research.

Interconnection: PJM Inside Lines (TC1 completion, Cycle 1 window, RRI); Modo Energy transition-cycle research; K&L Gates, Blank Rome, Baker Botts (FERC co-location order, Docket EL25-49).

Demand: PJM 2025 & 2026 Long-Term Load Forecast (via PJM Inside Lines, Modo, Utility Dive).

State policy: NJ BPU orders (Docket QO22080540) & Utility Dive; MD PSC / Next Generation Energy Act & Saul Ewing; VA enrolled HB2537 & JLARC Report 598; IL Public Act 104-0458 / Illinois Power Agency; PA PUC AEPS; OH HB15 (Kroll, Dickinson Wright).

Federal: IRS Clean Electricity Investment Credit & Notice 2026-15/IR-2026-23; Kirkland & Ellis, Williams Mullen, projectfinance.law (OBBBA/FEOC); Morgan Lewis (Section 301 tariff); FERC (Orders 841 & 2222).

Costs: NREL/TP-6A40-93281, "Cost Projections for Utility-Scale Battery Storage: 2025 Update"; Lazard LCOE+ June 2025 (LCOS v10).

All web sources accessed 15 July 2026. Full URLs are recorded in the accompanying master data file and in the pro forma's Sources tab. Figures marked VERIFIED are drawn from primary documents; those marked ESTIMATE are modeled or triangulated and labeled at the point of use.